Simulation and optimization model for the construction of electrical substations

One of the most complex construction projects is electrical substations. An electrical substation is an auxiliary station of an electricity generation, transmission and distribution system where voltage is transformed from high to low or the reverse using transformers. Construction of electrical sub...

Full description

Saved in:
Bibliographic Details
Main Author: Fayed, Rania
Format: Thesis
Published: AUC Knowledge Fountain 2017
Subjects:
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1867613407441584128
access_status_str Open Access
author Fayed, Rania
author_browse Fayed, Rania
author_facet Fayed, Rania
author_sort Fayed, Rania
collection Thesis
dc_rights_str_mv The author retains all rights with regard to copyright. The author certifies that written permission from the owner(s) of third-party copyrighted matter included in the thesis, dissertation, paper, or record of study has been obtained. The author further certifies that IRB approval has been obtained for this thesis, or that IRB approval is not necessary for this thesis. Insofar as this thesis, dissertation, paper, or record of study is an educational record as defined in the Family Educational Rights and Privacy Act (FERPA) (20 USC 1232g), the author has granted consent to disclosure of it to anyone who requests a copy.
description One of the most complex construction projects is electrical substations. An electrical substation is an auxiliary station of an electricity generation, transmission and distribution system where voltage is transformed from high to low or the reverse using transformers. Construction of electrical substation includes civil works and electromechanical works. The scope of civil works includes construction of several buildings/components divided into parallel and overlapped working phases that require variety of resources and are generally quite costly and consume a considerable amount of time. Therefore, construction of substations faces complicated time-cost-resource optimization problems. On another hand, the construction industry is turning out to be progressively competitive throughout the years, whereby the need to persistently discover approaches to enhance construction performance. To address the previously stated afflictions, this dissertation makes the underlying strides and introduces a simulation and optimization model for the execution processes of civil works for an electrical substation based on database excel file for input data entry. The input data include bill of quantities, maximum available resources, production rates, unit cost of resources and indirect cost. The model is built on Anylogic software using discrete event simulation method. The model is divided into three zones working in parallel to each other. Each zone includes a group of buildings related to the same construction area. Each zone-model describes the execution process schedule for each building in the zone, the time consumed, percentage of utilization of equipment and manpower crews, amount of materials consumed and total direct and indirect cost. The model is then optimized to mainly minimize the project duration using parameter variation experiment and genetic algorithm java code implemented using Anylogic platform. The model used allocated resource parameters as decision variables and available resources as constraints. The model is verified on real case studies in Egypt and sensitivity analysis studies are incorporated. The model is also validated using a real case study and proves its efficiency by attaining a reduction in model time units between simulation and optimization experiments of 10.25% and reduction in total cost of 4.7%. Also, by comparing the optimization results by the actual data of the case study, the model attains a reduction in time and cost by 13.6% and 6.3% respectively. An analysis to determine the effect of each resource on reduction in cost is also presented.
format Thesis
id oai:fount.aucegypt.edu:etds-1027
institution American University in Cairo (Egypt)
last_indexed 2026-06-10T12:35:39.635Z
license_str Other — see source repository
provenance_str_mv Harvested via OAI-PMH from AUC Knowledge Fountain — bepress
publishDate 2017
publishDateRange 2017
publishDateSort 2017
publisher AUC Knowledge Fountain
publisherStr AUC Knowledge Fountain
record_format dspace
source_str AUC Knowledge Fountain — bepress
spelling oai:fount.aucegypt.edu:etds-1027 Simulation and optimization model for the construction of electrical substations Fayed, Rania One of the most complex construction projects is electrical substations. An electrical substation is an auxiliary station of an electricity generation, transmission and distribution system where voltage is transformed from high to low or the reverse using transformers. Construction of electrical substation includes civil works and electromechanical works. The scope of civil works includes construction of several buildings/components divided into parallel and overlapped working phases that require variety of resources and are generally quite costly and consume a considerable amount of time. Therefore, construction of substations faces complicated time-cost-resource optimization problems. On another hand, the construction industry is turning out to be progressively competitive throughout the years, whereby the need to persistently discover approaches to enhance construction performance. To address the previously stated afflictions, this dissertation makes the underlying strides and introduces a simulation and optimization model for the execution processes of civil works for an electrical substation based on database excel file for input data entry. The input data include bill of quantities, maximum available resources, production rates, unit cost of resources and indirect cost. The model is built on Anylogic software using discrete event simulation method. The model is divided into three zones working in parallel to each other. Each zone includes a group of buildings related to the same construction area. Each zone-model describes the execution process schedule for each building in the zone, the time consumed, percentage of utilization of equipment and manpower crews, amount of materials consumed and total direct and indirect cost. The model is then optimized to mainly minimize the project duration using parameter variation experiment and genetic algorithm java code implemented using Anylogic platform. The model used allocated resource parameters as decision variables and available resources as constraints. The model is verified on real case studies in Egypt and sensitivity analysis studies are incorporated. The model is also validated using a real case study and proves its efficiency by attaining a reduction in model time units between simulation and optimization experiments of 10.25% and reduction in total cost of 4.7%. Also, by comparing the optimization results by the actual data of the case study, the model attains a reduction in time and cost by 13.6% and 6.3% respectively. An analysis to determine the effect of each resource on reduction in cost is also presented. 2017-02-01T08:00:00Z dissertation application/pdf https://fount.aucegypt.edu/etds/28 https://fount.aucegypt.edu/context/etds/article/1027/viewcontent/PhD_Rania_Fayed_AUC_Fall_2016.pdf The author retains all rights with regard to copyright. The author certifies that written permission from the owner(s) of third-party copyrighted matter included in the thesis, dissertation, paper, or record of study has been obtained. The author further certifies that IRB approval has been obtained for this thesis, or that IRB approval is not necessary for this thesis. Insofar as this thesis, dissertation, paper, or record of study is an educational record as defined in the Family Educational Rights and Privacy Act (FERPA) (20 USC 1232g), the author has granted consent to disclosure of it to anyone who requests a copy. Theses and Dissertations AUC Knowledge Fountain Genetic Algorithm NA
spellingShingle Genetic Algorithm
NA
Fayed, Rania
Simulation and optimization model for the construction of electrical substations
title Simulation and optimization model for the construction of electrical substations
title_full Simulation and optimization model for the construction of electrical substations
title_fullStr Simulation and optimization model for the construction of electrical substations
title_full_unstemmed Simulation and optimization model for the construction of electrical substations
title_short Simulation and optimization model for the construction of electrical substations
title_sort simulation and optimization model for the construction of electrical substations
topic Genetic Algorithm
NA
url https://fount.aucegypt.edu/etds/28
https://fount.aucegypt.edu/context/etds/article/1027/viewcontent/PhD_Rania_Fayed_AUC_Fall_2016.pdf
work_keys_str_mv AT fayedrania simulationandoptimizationmodelfortheconstructionofelectricalsubstations