Owner time and cost contingency estimation for building construction projects in Egypt

Time and cost overruns are an integral part of the construction projects. Both have several associated negative consequences to the project owners. Setting the right time and cost contingency is a major contributing factor to the success of the project as it should minimize/prevent budget and time o...

Full description

Saved in:
Bibliographic Details
Main Author: Nawar, Seif El-Din
Format: Thesis
Published: AUC Knowledge Fountain 2017
Subjects:
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1867613411777445888
access_status_str Open Access
author Nawar, Seif El-Din
author_browse Nawar, Seif El-Din
author_facet Nawar, Seif El-Din
author_sort Nawar, Seif El-Din
collection Thesis
dc_rights_str_mv The author retains all rights with regard to copyright. The author certifies that written permission from the owner(s) of third-party copyrighted matter included in the thesis, dissertation, paper, or record of study has been obtained. The author further certifies that IRB approval has been obtained for this thesis, or that IRB approval is not necessary for this thesis. Insofar as this thesis, dissertation, paper, or record of study is an educational record as defined in the Family Educational Rights and Privacy Act (FERPA) (20 USC 1232g), the author has granted consent to disclosure of it to anyone who requests a copy.
description Time and cost overruns are an integral part of the construction projects. Both have several associated negative consequences to the project owners. Setting the right time and cost contingency is a major contributing factor to the success of the project as it should minimize/prevent budget and time overruns. Project managers usually tend to allocate project time and cost contingency subjectively based on their previous experience and may not capture all projects specific factors that impact the contingency estimation. The competency of the project manager plays an important role in this case in determining the contingency percentage. The contingency estimation for a given project can hugely vary from one project manager to another. This research presents a fuzzy logic-based model that allows owners predict the project time and cost contingency reliably and accurately in Egypt. The most important factors affecting time and cost contingency have been identified and are defined as input variables for the model. The effect of these factors on the time and cost contingency, the output variables, have been determined and incorporated into the model via fuzzy rules. On the basis of the known effects of these factors, a fuzzy logic model is developed to automate the prediction process using MS Excel software. Several scenarios of the model are developed and subjected to initial testing using 10 actual projects data. Based on the initial testing, the best model was subjected to tuning in order to achieve the optimum model results in terms of accuracy and validity. Finally, the model is tested by applying it on new five actual construction projects which were not used in the initial testing nor tuning. The model results were found to be acceptable having an average validity percent of 84% and 81% for time and cost contingency, respectively. The proposed model allows the owners to [1] understand the effect of the project different factors on the contingency values, which in turn represent the degree of risk involved and accordingly, allows the owner to take necessary measures at the preconstruction stage to reduce the risks, [2] minimize the cost and time overrun through setting the right amount of contingency, [3] avoid tie up of excessive funds for the project, which can be used in others projects or activities, and [4] have higher confidence during the decision making process of whether to proceed or not to proceed with the project.
format Thesis
id oai:fount.aucegypt.edu:etds-1666
institution American University in Cairo (Egypt)
last_indexed 2026-06-10T12:35:43.583Z
license_str Other — see source repository
provenance_str_mv Harvested via OAI-PMH from AUC Knowledge Fountain — bepress
publishDate 2017
publishDateRange 2017
publishDateSort 2017
publisher AUC Knowledge Fountain
publisherStr AUC Knowledge Fountain
record_format dspace
source_str AUC Knowledge Fountain — bepress
spelling oai:fount.aucegypt.edu:etds-1666 Owner time and cost contingency estimation for building construction projects in Egypt Nawar, Seif El-Din Time and cost overruns are an integral part of the construction projects. Both have several associated negative consequences to the project owners. Setting the right time and cost contingency is a major contributing factor to the success of the project as it should minimize/prevent budget and time overruns. Project managers usually tend to allocate project time and cost contingency subjectively based on their previous experience and may not capture all projects specific factors that impact the contingency estimation. The competency of the project manager plays an important role in this case in determining the contingency percentage. The contingency estimation for a given project can hugely vary from one project manager to another. This research presents a fuzzy logic-based model that allows owners predict the project time and cost contingency reliably and accurately in Egypt. The most important factors affecting time and cost contingency have been identified and are defined as input variables for the model. The effect of these factors on the time and cost contingency, the output variables, have been determined and incorporated into the model via fuzzy rules. On the basis of the known effects of these factors, a fuzzy logic model is developed to automate the prediction process using MS Excel software. Several scenarios of the model are developed and subjected to initial testing using 10 actual projects data. Based on the initial testing, the best model was subjected to tuning in order to achieve the optimum model results in terms of accuracy and validity. Finally, the model is tested by applying it on new five actual construction projects which were not used in the initial testing nor tuning. The model results were found to be acceptable having an average validity percent of 84% and 81% for time and cost contingency, respectively. The proposed model allows the owners to [1] understand the effect of the project different factors on the contingency values, which in turn represent the degree of risk involved and accordingly, allows the owner to take necessary measures at the preconstruction stage to reduce the risks, [2] minimize the cost and time overrun through setting the right amount of contingency, [3] avoid tie up of excessive funds for the project, which can be used in others projects or activities, and [4] have higher confidence during the decision making process of whether to proceed or not to proceed with the project. 2017-06-01T07:00:00Z thesis application/pdf https://fount.aucegypt.edu/etds/667 https://fount.aucegypt.edu/context/etds/article/1666/viewcontent/2017.05.15_20Seif_20Eldin_20Nawar_20__20Master_20Thesis_20Report.pdf The author retains all rights with regard to copyright. The author certifies that written permission from the owner(s) of third-party copyrighted matter included in the thesis, dissertation, paper, or record of study has been obtained. The author further certifies that IRB approval has been obtained for this thesis, or that IRB approval is not necessary for this thesis. Insofar as this thesis, dissertation, paper, or record of study is an educational record as defined in the Family Educational Rights and Privacy Act (FERPA) (20 USC 1232g), the author has granted consent to disclosure of it to anyone who requests a copy. Theses and Dissertations AUC Knowledge Fountain Prediction Fuzzy Logic
spellingShingle Prediction
Fuzzy Logic
Nawar, Seif El-Din
Owner time and cost contingency estimation for building construction projects in Egypt
title Owner time and cost contingency estimation for building construction projects in Egypt
title_full Owner time and cost contingency estimation for building construction projects in Egypt
title_fullStr Owner time and cost contingency estimation for building construction projects in Egypt
title_full_unstemmed Owner time and cost contingency estimation for building construction projects in Egypt
title_short Owner time and cost contingency estimation for building construction projects in Egypt
title_sort owner time and cost contingency estimation for building construction projects in egypt
topic Prediction
Fuzzy Logic
url https://fount.aucegypt.edu/etds/667
https://fount.aucegypt.edu/context/etds/article/1666/viewcontent/2017.05.15_20Seif_20Eldin_20Nawar_20__20Master_20Thesis_20Report.pdf
work_keys_str_mv AT nawarseifeldin ownertimeandcostcontingencyestimationforbuildingconstructionprojectsinegypt