An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office

A Postgraduate Thesis Submitted to the Department of Constructed Technology and Management of the Kwame Nkrumah University of Science and Technology, Kumasi in partial fulfillment of the requirement for the Award of a Degree of Master of Science in Project Management.

Saved in:
Bibliographic Details
Main Author: Adukwei Habada, Wilhermina
Format: Thesis
Language:en_US
Published: 2021
Subjects:
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1867613139005079552
access_status_str Open Access
author Adukwei Habada, Wilhermina
author_browse Adukwei Habada, Wilhermina
author_facet Adukwei Habada, Wilhermina
author_sort Adukwei Habada, Wilhermina
collection Thesis
description A Postgraduate Thesis Submitted to the Department of Constructed Technology and Management of the Kwame Nkrumah University of Science and Technology, Kumasi in partial fulfillment of the requirement for the Award of a Degree of Master of Science in Project Management.
format Thesis
id oai:ir.knust.edu.gh:123456789/13660
institution KNUST (Ghana)
language en_US
last_indexed 2026-06-10T12:31:23.640Z
license_str Not specified — see source repository
provenance_str_mv Harvested via OAI-PMH from KNUSTSpace — Kwame Nkrumah University of Science & Technology (Ghana)
publishDate 2021
publishDateRange 2021
publishDateSort 2021
record_format dspace
source_str KNUSTSpace — Kwame Nkrumah University of Science & Technology (Ghana)
spelling oai:ir.knust.edu.gh:123456789/13660 An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office Adukwei Habada, Wilhermina Stakeholder Management, Construction, Project Consultant, Project Consultant, Contractor, Employees. A Postgraduate Thesis Submitted to the Department of Constructed Technology and Management of the Kwame Nkrumah University of Science and Technology, Kumasi in partial fulfillment of the requirement for the Award of a Degree of Master of Science in Project Management. This current study was aimed at examining the effects of stakeholder management on project performance using the case study of the construction of Access Bank head office building in Accra. Objectives for the study included: to identify the stakeholder management strategies, policies and practices adopted on the project, to investigate the effects of stakeholder management on the project delivery and to establish the stakeholder management challenges encountered during the course of the head office project. To operationalize this broad objective, the case study approach was used and the study employed the purposive sampling technique which enabled the researcher to use their judgment and intuition to collect data from a specific group. A semi structured interview was administered to 4 (four) key personnel, thus the Project Consultant, the project Contractor and Access bank who were deemed to be informative, knowledgeable and could speak on the subject matter of the study. The data was collected in a week and the use of the Thematic analysis was applied to enable the study to detect the patterns and themes from the information gathered and in the process discuss the finding. The study found that there were many diverse stakeholders with a multiplicity of interests and expectations and that overall, these stakeholders were consulted and involved throughout the duration of the project. It was again found that project leaders and supervisors used different methods and practices to engage, involve and manage stakeholders. In relation to the second objective of establishing the effect of stakeholder management practices on project success at Access bank, it was found that overall; stakeholder management facilitated the timely delivery of the Head office Project. In relation to the third objective, it was established that the project team encountered several challenges such as language barriers, failure to identify certain stakeholders, delays in the release of funds, unreasonable demands and failure to meet regularly with salient stakeholders to discuss issues pertinent to the execution of the project. Recommendations made to improve upon Access bank’s stakeholder strategies included the bank taking time and investing in the most appropriate methods of identifying specific stakeholder needs, that Access bank should employ different methods of identifying and communicating with different stakeholders so that they understand and appreciate all issues being discussed in relation to the project and that all team members on site should be regularly trained on key issues and areas such as safety, preservation of resources, waste reduction, and treatment of waste materials. KNUST 2021-04-16T12:24:33Z 2023-04-19T02:48:52Z 2021-04-16T12:24:33Z 2023-04-19T02:48:52Z 2021-04-16 Thesis https://ir.knust.edu.gh/handle/123456789/13660 en_US application/pdf
spellingShingle Stakeholder Management,
Construction,
Project Consultant,
Project Consultant,
Contractor,
Employees.
Adukwei Habada, Wilhermina
An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office
title An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office
title_full An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office
title_fullStr An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office
title_full_unstemmed An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office
title_short An Empirical Analysis of the Effects of Stakeholder Management on Construction Project Delivery: Case-Study of the Construction of Access Bank Head Office
title_sort empirical analysis of the effects of stakeholder management on construction project delivery case study of the construction of access bank head office
topic Stakeholder Management,
Construction,
Project Consultant,
Project Consultant,
Contractor,
Employees.
url https://ir.knust.edu.gh/handle/123456789/13660
work_keys_str_mv AT adukweihabadawilhermina anempiricalanalysisoftheeffectsofstakeholdermanagementonconstructionprojectdeliverycasestudyoftheconstructionofaccessbankheadoffice
AT anempiricalanalysisoftheeffectsofstakeholdermanagementonconstructionprojectdeliverycasestudyoftheconstructionofaccessbankheadoffice
AT adukweihabadawilhermina empiricalanalysisoftheeffectsofstakeholdermanagementonconstructionprojectdeliverycasestudyoftheconstructionofaccessbankheadoffice
AT empiricalanalysisoftheeffectsofstakeholdermanagementonconstructionprojectdeliverycasestudyoftheconstructionofaccessbankheadoffice