Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant

Background: Projects have become larger, technologically more sophisticated and are organised with a higher number of contractors and partners, compared to 40 years ago. The majority of large, complex capital projects often incur significant cost/budget and schedule overruns. Delays and cost overrun...

Full description

Saved in:
Bibliographic Details
Main Author: Mabumbulu, Noxolo
Other Authors: Jay, Ian
Format: Thesis
Language:English
Published: Department of Construction Economics and Management 2017
Subjects:
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1867613993849323520
access_status_str Open Access
author Mabumbulu, Noxolo
author2 Jay, Ian
author_browse Jay, Ian
Mabumbulu, Noxolo
author_facet Jay, Ian
Mabumbulu, Noxolo
author_sort Mabumbulu, Noxolo
collection Thesis
description Background: Projects have become larger, technologically more sophisticated and are organised with a higher number of contractors and partners, compared to 40 years ago. The majority of large, complex capital projects often incur significant cost/budget and schedule overruns. Delays and cost overruns are seemingly, the rule rather than an exception these days. Research shows that one of the reasons for project failure is the increasing complexity of projects or an underestimation of the project complexity. There is therefore a fundamental need to develop a tool or model that will assist project managers to measure complexity within their projects Research Purpose: To define project complexity, develop a model or tool to measure complexity within projects and to improve the understanding of the dimensions of project complexity. Research Methodology: The case study methodology was employed, and the unit of analysis was the refuelling outage in a nuclear power generating plant. Focus group was adopted as a technique to gather information. A group of project managers with wealth of knowledge in refuelling outages were assembled. They were given the complexity assessment matrix to assess their respective subprojects, in order to rate the refuelling outage project Findings: Two main scientific approaches to project complexity, namely; descriptive complexity and perceived complexity were established. Descriptive complexity considers complexity as an intrinsic property of a system. Perceived complexity considers complexity as subjective, since the complexity of a system is understood through the perception of an observer and both approaches can coexist. There are vital layers of complexity such as: social, cultural, operative and cognitive complexity that must be considered when dealing with complexity within projects. A three dimensional model that encompasses the complexity dimensions (origin of project complexity), severity factors (the extent to which complexity dimension will be a problem) and the nature of interdependences (pooled, sequential, and reciprocal) was developed. This model was used to assess complexity of the refuelling outage in a power generating plant. The results of this assessment indicated that this project is a very complex project.
format Thesis
id oai:open.uct.ac.za:11427/23700
institution University of Cape Town (South Africa)
language eng
last_indexed 2026-06-10T12:44:58.895Z
license_str Not specified — see source repository
provenance_str_mv Harvested via OAI-PMH from UCTD — University of Cape Town Open Access Repository
publishDate 2017
publishDateRange 2017
publishDateSort 2017
publisher Department of Construction Economics and Management
publisherStr Department of Construction Economics and Management
record_format dspace
source_str UCTD — University of Cape Town Open Access Repository
spelling oai:open.uct.ac.za:11427/23700 Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant Mabumbulu, Noxolo Jay, Ian Project Management Background: Projects have become larger, technologically more sophisticated and are organised with a higher number of contractors and partners, compared to 40 years ago. The majority of large, complex capital projects often incur significant cost/budget and schedule overruns. Delays and cost overruns are seemingly, the rule rather than an exception these days. Research shows that one of the reasons for project failure is the increasing complexity of projects or an underestimation of the project complexity. There is therefore a fundamental need to develop a tool or model that will assist project managers to measure complexity within their projects Research Purpose: To define project complexity, develop a model or tool to measure complexity within projects and to improve the understanding of the dimensions of project complexity. Research Methodology: The case study methodology was employed, and the unit of analysis was the refuelling outage in a nuclear power generating plant. Focus group was adopted as a technique to gather information. A group of project managers with wealth of knowledge in refuelling outages were assembled. They were given the complexity assessment matrix to assess their respective subprojects, in order to rate the refuelling outage project Findings: Two main scientific approaches to project complexity, namely; descriptive complexity and perceived complexity were established. Descriptive complexity considers complexity as an intrinsic property of a system. Perceived complexity considers complexity as subjective, since the complexity of a system is understood through the perception of an observer and both approaches can coexist. There are vital layers of complexity such as: social, cultural, operative and cognitive complexity that must be considered when dealing with complexity within projects. A three dimensional model that encompasses the complexity dimensions (origin of project complexity), severity factors (the extent to which complexity dimension will be a problem) and the nature of interdependences (pooled, sequential, and reciprocal) was developed. This model was used to assess complexity of the refuelling outage in a power generating plant. The results of this assessment indicated that this project is a very complex project. 2017-01-30T10:24:02Z 2017-01-30T10:24:02Z 2016 Master Thesis Masters MSc (Eng) http://hdl.handle.net/11427/23700 eng application/pdf Department of Construction Economics and Management Faculty of Engineering and the Built Environment University of Cape Town
spellingShingle Project Management
Mabumbulu, Noxolo
Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant
thesis_degree_str Master's
title Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant
title_full Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant
title_fullStr Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant
title_full_unstemmed Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant
title_short Project complexity and how to effectively measure complexity in projects: the case of a refuelling outage in a nuclear power generating plant
title_sort project complexity and how to effectively measure complexity in projects the case of a refuelling outage in a nuclear power generating plant
topic Project Management
url http://hdl.handle.net/11427/23700
work_keys_str_mv AT mabumbulunoxolo projectcomplexityandhowtoeffectivelymeasurecomplexityinprojectsthecaseofarefuellingoutageinanuclearpowergeneratingplant