4D schedule generation for flat slab BIM models

Planning & scheduling has made some amazing progress in the past 20 years, a period when numerous site engineers felt that utilizing formal planning was unnecessary to everyday operations and a period expending diversion. From that point forward, it has turned into a necessary piece for most project...

Full description

Saved in:
Bibliographic Details
Main Author: Hosny, Amir Ossama
Format: Thesis
Published: AUC Knowledge Fountain 2017
Subjects:
Tags: Add Tag
No Tags, Be the first to tag this record!
_version_ 1867613409557610496
access_status_str Open Access
author Hosny, Amir Ossama
author_browse Hosny, Amir Ossama
author_facet Hosny, Amir Ossama
author_sort Hosny, Amir Ossama
collection Thesis
dc_rights_str_mv The author retains all rights with regard to copyright. The author certifies that written permission from the owner(s) of third-party copyrighted matter included in the thesis, dissertation, paper, or record of study has been obtained. The author further certifies that IRB approval has been obtained for this thesis, or that IRB approval is not necessary for this thesis. Insofar as this thesis, dissertation, paper, or record of study is an educational record as defined in the Family Educational Rights and Privacy Act (FERPA) (20 USC 1232g), the author has granted consent to disclosure of it to anyone who requests a copy.
description Planning & scheduling has made some amazing progress in the past 20 years, a period when numerous site engineers felt that utilizing formal planning was unnecessary to everyday operations and a period expending diversion. From that point forward, it has turned into a necessary piece for most projects, yet remains a period consuming, mistake inclined and manually initialized tool. This process is dependent on the method statements and the construction logic that are defined at the beginning of the project which will help in the development of the time schedule of works. Contractors use a set of defined productivity rates for the different construction activities that satisfy the required finish milestones specified by the contract; overcrowding and overmanning are not taken into considerations between labor in the project when selecting the productivity rates for the activities. Moreover, the site management team takes a huge amount of efforts and time to optimize the formwork area available and their reuse in different parts of the project. This research was divided into three stages; first stage was the collection of data stage which is mainly the interviews stage where interviews were held with about 14 experts. Second stage was the model was developed based on a number of algorithms to develop the time schedule and the cost estimation of a BIM model by minimum user inputs as well as including many parameters that are not being taken into considerations by planners in the contractors or the engineers side. Parameters include: the area of formwork available for construction in m2, the reuse of formwork in different zones for cost reduction, crowdedness and overmanning reduction for increase of productivity per crew, automatic zoning of building with relation to the construction joints in a building, optimization of number of crews and their allocation and the enhancement between the area of formwork available for construction and the number of crews. The model was validated with a case study project where the approved baseline schedule and the used method statement were compared to the model outputs. The results highlight the model's robust features in terms of: generating construction zones that account for the available amount of formwork and their reuse while minimizing the construction cost, optimizing the productivity rate per crew while considering the crowdedness of the job location per construction zone and over all optimizing the construction schedule in terms of time, cost and generating different method statement through formwork movements. Thus, using this model, a contractor could significantly improve his productivity, effectively generate construction schedules and method statements of a project.
format Thesis
id oai:fount.aucegypt.edu:etds-1392
institution American University in Cairo (Egypt)
last_indexed 2026-06-10T12:35:41.195Z
license_str Other — see source repository
provenance_str_mv Harvested via OAI-PMH from AUC Knowledge Fountain — bepress
publishDate 2017
publishDateRange 2017
publishDateSort 2017
publisher AUC Knowledge Fountain
publisherStr AUC Knowledge Fountain
record_format dspace
source_str AUC Knowledge Fountain — bepress
spelling oai:fount.aucegypt.edu:etds-1392 4D schedule generation for flat slab BIM models Hosny, Amir Ossama Planning & scheduling has made some amazing progress in the past 20 years, a period when numerous site engineers felt that utilizing formal planning was unnecessary to everyday operations and a period expending diversion. From that point forward, it has turned into a necessary piece for most projects, yet remains a period consuming, mistake inclined and manually initialized tool. This process is dependent on the method statements and the construction logic that are defined at the beginning of the project which will help in the development of the time schedule of works. Contractors use a set of defined productivity rates for the different construction activities that satisfy the required finish milestones specified by the contract; overcrowding and overmanning are not taken into considerations between labor in the project when selecting the productivity rates for the activities. Moreover, the site management team takes a huge amount of efforts and time to optimize the formwork area available and their reuse in different parts of the project. This research was divided into three stages; first stage was the collection of data stage which is mainly the interviews stage where interviews were held with about 14 experts. Second stage was the model was developed based on a number of algorithms to develop the time schedule and the cost estimation of a BIM model by minimum user inputs as well as including many parameters that are not being taken into considerations by planners in the contractors or the engineers side. Parameters include: the area of formwork available for construction in m2, the reuse of formwork in different zones for cost reduction, crowdedness and overmanning reduction for increase of productivity per crew, automatic zoning of building with relation to the construction joints in a building, optimization of number of crews and their allocation and the enhancement between the area of formwork available for construction and the number of crews. The model was validated with a case study project where the approved baseline schedule and the used method statement were compared to the model outputs. The results highlight the model's robust features in terms of: generating construction zones that account for the available amount of formwork and their reuse while minimizing the construction cost, optimizing the productivity rate per crew while considering the crowdedness of the job location per construction zone and over all optimizing the construction schedule in terms of time, cost and generating different method statement through formwork movements. Thus, using this model, a contractor could significantly improve his productivity, effectively generate construction schedules and method statements of a project. 2017-02-01T08:00:00Z thesis application/pdf https://fount.aucegypt.edu/etds/393 https://fount.aucegypt.edu/context/etds/article/1392/viewcontent/Final_20Thesis_20Report_20Rev_20I_2019_7_2016.pdf The author retains all rights with regard to copyright. The author certifies that written permission from the owner(s) of third-party copyrighted matter included in the thesis, dissertation, paper, or record of study has been obtained. The author further certifies that IRB approval has been obtained for this thesis, or that IRB approval is not necessary for this thesis. Insofar as this thesis, dissertation, paper, or record of study is an educational record as defined in the Family Educational Rights and Privacy Act (FERPA) (20 USC 1232g), the author has granted consent to disclosure of it to anyone who requests a copy. Theses and Dissertations AUC Knowledge Fountain 4D BIM Generation Automated Construction Scheduling
spellingShingle 4D BIM Generation
Automated Construction Scheduling
Hosny, Amir Ossama
4D schedule generation for flat slab BIM models
title 4D schedule generation for flat slab BIM models
title_full 4D schedule generation for flat slab BIM models
title_fullStr 4D schedule generation for flat slab BIM models
title_full_unstemmed 4D schedule generation for flat slab BIM models
title_short 4D schedule generation for flat slab BIM models
title_sort 4d schedule generation for flat slab bim models
topic 4D BIM Generation
Automated Construction Scheduling
url https://fount.aucegypt.edu/etds/393
https://fount.aucegypt.edu/context/etds/article/1392/viewcontent/Final_20Thesis_20Report_20Rev_20I_2019_7_2016.pdf
work_keys_str_mv AT hosnyamirossama 4dschedulegenerationforflatslabbimmodels